Growatt New Energy.CO.LTD
www.ginverter.com
28
should locate between two forks of the forklift. The big-size inverter may block driver's sight, and
it shall be treated with cooperation of the aid personnel.
4.3.2 Movement and installation of bare machine
[Demolish the package of inverter]
Please demolish the packaged cabinet of the equipment according to the following procedures:
Procedure 1:
Demolish the wood side and roof of the packaged cabinet
Procedure 2:
Demolish the out-set package material on the machine
Procedure 3:
Demolish the fastening screws between the machine and the pallet
①
Demolish the front and back cover lids of the pedestal;
②
Screw off the hold-down nuts at the bottom of the wood pallet;
③
Remove the screws, and the inverter will depart from the wood pallet.
The inverter must be installed on the foundation or foundation plate, therefore, all fastening points
(wall anchor and bolt) must be at their correct positions before installation. Mounting dimension
of foot margin on foundation is shown in Figure.
Figure 4-3-2-1
[Movement and installation of bear machine]
The inverter with demolished package can be moved with forklift, hoisting crane, slide rail or
crane.
If the package demolished place is far from the final installation place, it can be transported with
forklift containing wood pallet. It is shown in Figure.