GR
-
UM
-
193
-
A
-
03
PV+
PV-
1
2
Customer
can
read
more
information
by push button.
Mark
Describe
Explain
Touch mark
Single touch
Switch the display interface or the
current number plus 1
Double touch
Enter the setting state or confirm
Triple touch
Return to the previous display interface
Long press for 5s
Confirm Country setting or Number
recover default value
Inverter status indicator
Red
Fault
Green
Normal operation
Red light flashing
Warning
It can display the basic information of inverter through OLED display screen
(PV/AC voltage,PV power,ACcurrent,total power,generating capacity, etc.).
9.
8.
Note:
1.Before installing the PV terminal, please
double-check that the PV input voltage and
current do not exceed the MPPT limits.
2.When installing the PV terminal, pay
attention to the difference between the
positive and negative poles and the one-to-
one correspondence between the terminals
and the machine.
3.There is a "click" sound when the terminal
is connected,please gently pulling the PV
wire to make sure there is no loose or
pulling off.
3.3.3 Communication cable installation
Click
Download
Manual
Growatt New Energy
3.3.2 Plug in PV terminal
The
Inverter
side
The
Inverter
side
Unclock the housing
Click!
Click!
Connecting Meter
4.
The following table describes how we can connect EASTRON meter (SDM230-Modbus)to inverter:
Meter Pin NO.
Description
Meter Connection
1
2
3
4
5
6
L-in
L-out
N-in
N-out
RS485A
RS485B
Grid L
AC connector & Load L
Grid N
AC connector & Load N
COM Pin 7 RS485A2
COM Pin 8 RS485B2
Note:
6.
Power on and off steps
5.
Post-installation check
No.
Acceptance criteria
No.
Acceptance criteria
1
The inverter is installed correctly, firmly and reliably.
6
The RS485 communication cable is installed correctly and firmly.
2
The ground wire connected well and the connection is firm
and reliable.
7
The cable tie port is trimmed well without leaving sharp
corners,meets the requirements of the user.
3
All switches are in the OFF state.
8
All exposed terminals are well protected and there are no vacant
ports.
4
All wiring is correct and securely connected.
9
Pay attention to clean up all construction residues.
5
The wiring of the cable is reasonable, meets the
requirements, and there is no phenomenon of broken skin.
7.
Status of PV grid inverter
Service and contact
Export limitation setting
Exporlimit
OFF
ON
Password
123
Set parameter
General
Advanced
Meter
CT
ExportLimit Rate
XXX.X%
Set OK
Under the permission given by your energy
provider, the ratio of your system output
power divided by the rated power of the
inverter is called Export Limit Rate. For
instance, if the energy provider only
accepts 2.4kW from your 3kW system, then
the Export Limit Rate of 3kW inverter is
80.0%.
1
The Inverter
side
The Inverter
side
The Inverter
side
COM Port Pin Definitions
COM Port
Definition
1
NA
This pin is no signal
2
NA
3
RS 485A1
Signal for communication
4
RS 485B1
5
CT-P
Signal for export limitation
(Optional)
6
CT-N
7
RS 485A2
Signal for smart meter
8
RS 485B2
DRM port Pin Definitions
RJ45 Plug
RRCR Definition
Active
power
DRM Definition
1
K1
–
Relay
1
output
0
DRM5
2
K2
–
Relay
1
output
30%
DRM6
3
K3
–
Relay
1
output
60%
DRM7
4
K4
–
Relay
1
output
100%
DRM8
5
Relays common node
/
REFGEN
6
Not
connecte
/
COM/DRM0
7
Not
connected
/
/
8
Not
connected
/
/
1.When laying out signal cables, separate them from power cables to avoid strong signal interference sources
2.Do not mix the connector to the DRM port and the connector to the COM port.
Note
:
1
2
3
4
5
6
7
8
K1
K2
K3
K4
1 2345678
RJ45 Plug
RRCR
Note:
①
For Australian market, installers can connect pin3 or pin4 to the neutral links/bars.
Before
turning
the
inverter
on
,
please
make
sure
the
PV
input
voltage
and
current
are
within
the
MPPT
limits
.
Follow
the
steps
below
to
turn
the
inverter
on
:
1
.
Switch
on
the
build
-
in
DC
isolator
at
the
bottom
of
the
inverter
.
2
.
Switch
on
the
PV
Array
and
DC
isolator
next
to
your
inverter
,
if
you
can
not
find
this
switch
,
skip
this
step
.
3
.
Switch
on
the
Solar
AC
isolator
if
the
inverter
is
more
than
3
meters
away
from
your
switchboard
.
4
.
Switch
on
the
solar
supply
main
switch
in
the
switch
board
.
To
shut
down
your
system
,
follow
this
guide
in
reverse
order
Shenzhen Growatt New Energy Co., Ltd
4-13/F,Building A,Sino-German(Europe) Industrial Park,
Hangcheng Ave,Bao’an District, Shenzhen, China
+86 0755 2747 1942
www.ginverter.com
T
E
W
service@ginverter.com