Commissioning
7
CAUTION
WARNING
DANGER
Do not disconnect the DC connectors under load.
Improper operation during the wiring process can cause fatal injury to
operator or unrecoverable damage to the inverter. Only qualified
personnel can perform the wiring work.
Damage to the inverter due to moisture and dust penetration
Ø
Ø
Make sure the cable gland has been tightened firmly.
If the cable gland are not mounted properly, the inverter can be
destroyed due to moisture and dust penetration. All the warranty
claim will be invalid.
Requirements
:
ü
ü
ü
ü
The AC cable is correctly connected.
The DC cable is correctly connected.
The communication cable is correctly connected.
The country is set correctly.
7.1
Start the inverter
7.1.1 Touch control
7.1.2 Country/Area and Region setting
Touch
Single touch
Double touch
Three touch
Hold 5s
Description
Switch display or 1
Enter
Previous menu
C o n f i r m c o u n t r y s e t t i n g o r
Number recover default value
Information
Country/Area and Region setting
When the inverter start up,we need to select the right country,if we
don't select any country, the inverter will run under AS/NZS4777.2 as
default for Australia & Region A,or run under VDE0126-1-1 for other
region after 30s.
When inverter powered on, OLED will light automatically. Once the PV power is
sufficient, OLED displays the following:
31
32
6.10 Earth Fault Alarm
The inverter complies with IEC62109-2.When the Earth fault occurs,the Red LED will
light up.The buzzer in the inverter will keep ringing unless the fault condition is
cleared(This function is only avilable for Australia and New Zealand).
Fig 6.23