background image

5 Energy Management System

Notice: First time install the energy storage system, charge the battery for at least 1 hours

 or up to 60% SOC before powering off the system.  This action will keep up the battery 

power to avoid running out while waiting for PTO.

There are two ways to charge the battery. 

Ø

The first is to connect the PV array to the PV of the inverter and turn off the AC output 

     breaker of the inverter.     

Ø

The second method is to Wake up the battery via the battery's force-wake switch 

button

The forced wake-up switch button of the LG battery is at the bottom of the 

inverter wiring frame, and the forced wake-up switch button of the ARO battery is on the 

ARO battery cabinet

 and connect SYN 200-XH-US to the grid without any 

PV input, set the EMS mode of the system to 

TOU Battery Charging (5.2.3), and turn

on the AC charging function (5.2.2).

5.1 Management System Mode Introduction

The MIN 3K-11.4K TL-XH-US system provides four energy storage modes to choose from.

Storage Mode

Description

TOU Battery 

Charging

Charge battery from PV production and grid power (if needed) until 

it is full. Only then use PV production for self-consumption and grid
export

TOU Battery 

Discharging

If PV Production < Inverter Maximum Production (nameplate or 
limited power), discharge battery for self-consumption and grid 
export until the inverter reaches its power limit or max battery 
discharge power.

Maximum self-

consumption

Use PV production for self-consumption, then charge/discharge 

battery as needed to maximize self-consumption

Maximum self-

consumption

Export Limit

The power output from the system to the grid is limited at the

 

set

 

value

5.2 Energy Management System setting

For the photovoltaic energy storage system, several functions of the system need to set 
after the first installation and power-up.

11

12

Battery

Bus+

Bus-

Bat+

Bat-

3

Battery

Bus+

Bus-

Bat+

Bat-

2

Battery

Bus+

Bus-

Bat+

Bat-

-

2

Battery

Bus+

Bus-

Bat+

Bat-

Summary of Contents for MIN 3K-11.4KTL-XH-US

Page 1: ...00 Download Manual Growatt New Energy Growatt USA Inc 9227 Reseda Blvd 435 Northridge CA 91324 USA 1 866 686 0298 www growatt america com T E usaservice ginverter com W MIN 3K 11 4K TL XH US Commissi...

Page 2: ...rk 3 Grid Code Mapping Table 4 Wi Fi Network Configuration 5 Energy Management System 5 1 Management System Mode Introduction 5 2 Energy Management System setting 6 Battery Life Maintenance 7 Troubles...

Page 3: ...ergen cy stop switch AC SYN 200 XH US Optional Optional MIN3 11 4KTL XH US Inverter MIN3 11 4KTL XH US Inverter PV MIN XH US Inverter L1 L2 N Back up L1 L2 AC Grid Ground bar L1 PV MIN XH US Inverter...

Page 4: ...nergy storage UP TO 2 ATS SYN 200 XH US EPS switching Smart meter SM US 200 Energy management Button RSD Button Rapid shutdown Accessory included in the package Power on the system according to the MI...

Page 5: ...onnect the inverter with built in WIFI at close range We can view the inverter system information and system fouction settings with it 2 3 Connecting to Local Wi Fi Network The steps for using APP are...

Page 6: ...nsuccessful and you will need to reconnect the build in WIFI of the inverter by turning off Wifi setting in the phone and turn on again OR power cycle the system Also keep the mobile phone within 3 me...

Page 7: ...low voltage power grid 7 PRC Quebec 208 Canada Quebec low voltage power grid 8 PRC Quebec 240 Canada Quebec low voltage power grid 9 RULE21 208 US California low voltage power grid 10 RULE21 240 US Ca...

Page 8: ...nagement System Mode Introduction The MIN 3K 11 4K TL XH US system provides four energy storage modes to choose from Storage Mode Description TOU Battery Charging Charge battery from PV production and...

Page 9: ...s Disabled 1 Tap in Charge and Discharge Management 2 Find Enable AC Charging 3 Tap in ON OFF button 14 5 2 1 Power Sensor Setting If an electric meter is installed in the system please set Factory De...

Page 10: ...XH US needs to set the off grid and electric meter enable Factory Default is disable Off Grid enable settings are as follows please refer to chapter 5 2 1 for meter settings 1 Tap in EMS 2 Tap in Tim...

Page 11: ...eriods you need to operate step 4 5 6 multiple times You can also set the energy storage mode for special days if necessary Battery Life Maintenance 6 a TUnplug Battery power Battery Communication cab...

Page 12: ...estored contact manufacturer Error 203 PV Isolation Low PV panel insulation problem 1 Check PV panel and wiring Error 204 PV Reversed PV positive and negative are reversed 1 After shutdown Check the i...

Page 13: ...terface and log into the account after the registration is completed 8 2 Create a power plant a When you log into your account for the first time you will be prompted to register a power plant b Click...

Page 14: ...ode through WeChat or IOS s Camera then download the APP d APP Store Search for ShinePhone from app stores download the installation package and install the ShinePhone app by following the instruction...

Page 15: ...ur PV system would be authorized and monitored by your installer 3 Fill the plant info 4 Continue fill the plant info 5 Tap in skip 6 Add collector 26 25 7 The Plant page display the list of plants un...

Reviews: