4
Installation
Unpacking and Inspection
Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You
should have received the following items in the package:
The unit x1
User manual x 1
Communication cable x 1
Preparation
Before connecting all wiring, please take off bottom cover by removing eight screws as shown below.
Mounting the Unit
Consider the following points before selecting where to install:
Do not mount the inverter on flammable construction materials.
Mount on a solid surface
Install this inverter at eye level in order to allow the LCD
display to be read at all times.
The ambient temperature should be between 0°C and 50°C to
ensure optimal operation.
The recommended installation position is to be adhered to the
wall vertically.
Be sure to keep other objects and surfaces as shown in the
right diagram to guarantee sufficient heat dissipation and to
have enough space for removing wires.
SUITABLE FOR MOUNTING ONCONCRETE OR
OTHER NON-COMBUSTIBLE SURFACE ONL
4~6KW 8~12KW
Install the unit by screwing the six setscrews.