Set Ground Posts
Drawing may show layout of a different length. Refer to
Quick Start section located in the back of these instructions
for on-center measurements and post layout for your frame.
MARK THE SITE AND DIG POST HOLES
These steps describe marking all post hole locations and digging
the holes. For some sites, it may not be possible to complete the
procedure in this manner. An alternative procedure such as working
from one end of the building toward the other may be necessary.
Determine the best procedure based on the site and other factors
and proceed as needed.
NOTE:
Refer to the Quick Start Section located near the back
of these instructions for the Side Profile and related diagrams
.
Complete these steps:
1. Stake the outline of the building using string line and batter boards. Set batter boards 3' back from the building
corners. Check to ensure that the building layout is square. Cover or panels (if equipped) will not install properly if
the building frame is not square once assembled.
2. Consult the diagrams in the Quick Start section to verify the frame length and width dimensions and to accurately
position the ground posts.
3. Guided by the string line, use a flag or stake to mark each ground post hole location.
4. Move the string line and dig a post hole a minimum of two feet (2') deep
or to a depth that is
below the geographic
frost line.
Consult local building codes. A power auger works best.
Minimum hole diameter is 12"
.
5. After digging all holes, reattach the string line to the batter boards and use it as a guide to set and align the
ground posts.