8
H5_30_Wide_HT_Roll_Up
Revision date: 06.28.19
Drawing may show layout of a different length. Refer to Quick Start section located in the back of these instructions for on-center
measurements and post layout for your frame. Drawing is not to scale.
Complete these steps:
1. Stake the outline of building using string line and batter boards. Set batter boards 3' back from building corners.
2. Check to ensure building layout is square. Cover will not install properly if building frame is not square once
assembled.
3. Consult diagrams in the Quick Start section to verify frame length and width dimensions and to accurately position
ground posts.
4. Set string line to use as a guide when driving ground posts. Ensure line is level. Drive ground posts 24" below
finished grade. All post tops to be same height above finished grade to properly assemble frame.
5. Guided by string line, use a flag or stake to mark each ground post location.
6. Continue by driving ground posts.
Ground Posts
On-Center
Rafter Spacing
On-Center Width of
Building/Rafter
Markers tied to string line
or stakes in ground to mark
ground post locations.
The following steps describe one way to layout the site and mark ground post positions. There are others. Consult the
services of a qualified contractor experienced with the construction of similar buildings to prevent unforeseen issues.