10. 4 x 5 Distributor Platform (Optional)
82
PNEG-1807CE
CE Compliant 16"-24" Bucket Elevator Platform and Ladder “X” Series
Install Handrail Posts - Non-Entrance Side
1. Install the remaining two (2) “W” corner posts to the corners on the non-entrance side of the decking
using four (4) 5/16" x 3/4" flange bolts and nuts per post.
2. Install platform post (HP1648HCP) to the inside corner of the decking near the entrance to the
platform using four (4) 5/16" x 3/4" flange bolts and nuts.
3. Attach side posts (HP1648HP) to the decking at the entrance to the platform using two (2)
5/16" x 3/4" flange bolts and nuts per post.
4. Install distributor handrail support to the side post on the inside, located closest to the trunking
through holes 3 and 4 counting from the top of the post. Use two (2) 5/16" x 3/4" flange bolts and nuts
to fasten in place.
Figure 10L
Ref #
Part #
Description
Ref #
Part #
Description
A
HP1648HP
Head/Distributor Side Post
D
DSP1648HS
Distributor Handrail Support
B
HP1648HWP
Head/Distributor “W” Post
E
S-6606
5/16" x 3/4" Flange Bolt
C
HP1648HCP
Platform Post
F
S-10268
5/16" Flange Nut
NOTE: Right hand shown.