Installing the Auxiliary Intermediate Well (Optional)
What You Should Know
If the center well becomes plugged during gravity unloading, this option allows the bin to still be unloaded
until the plugged center well can be addressed. This control option allows the end user to independently
control the intermediate closest to the center well
1. Install the auxiliary control rod guides (73) to all intermediate wells (65) using the HHTB bolts (71)
and nylock nuts (72).
NOTE:
The control rod guide must mount to the intermediate well as shown for proper rod alignment
to gate and wall flange.
Figure 3-11
Installing the auxiliary rod guide to intermediate well
65
Intermediate well
72
1/2 in. nylock nut
71
1/2 x 1-1/2 in. HHTB bolt
73
Auxiliary control rod guide
26
PNEG-2108
8" and 10" Standard Duty and IW Standard Duty