LPA 3000XLS/3200XLS Instruction Manual
15
Connect Operator Power Cables
Step 2
Loosen sealing nuts on strain relief hubs at
bottom of control box. Insert power cables
into control box through strain reliefs. Thread
approximately 6” to 8” of the power cables into
the control box and retighten sealing nuts until
the power cables lock into place.
Sealing Nut
Hub
Lock Nut
Strain Relief
Step 1
Review the Installation Overview illustration below before proceeding.
Cut a slot into the driveway to accommodate 3/4” PVC conduit (not provided). The buried conduit will
protect the SECOND operator power cable from automobile tires, lawn mower blades, weed eaters, and
grazing animals. Pull the SECOND operator power cable through the conduit, up to the Control Box.
Receiver
PVC conduit (not included)
to protect SECOND operator
power cable from lawn mowers
and weed eaters.
Control Box
Power Cable
from SECOND
Gate Operator
GATES IN THE OPEN POSITION
WITH OPERATORS INSTALLED
MASTER Gate Operator
Power Cable
from MASTER
Gate Operator
SECOND Gate Operator
Power Cable from
Second Operator
Power Cable from
Master Operator
Strain Relief