background image

 

36 

M9000-AI-E16 

Figure 3-3 Front view 

 

(1) SEM section 

(2) Interface switch module/AI security engine module section 

(3) Switching fabric module section 

 

Summary of Contents for SecPath M9000-AI

Page 1: ...E8 gateway 17 Installing a switching fabric module for an M9000 AI E16 gateway 18 Installing interface modules or service modules 19 Installing interface switch modules or AI security engine modules...

Page 2: ...s and accessories As a best practice keep the packing materials for later moving or shipment ESD prevention To prevent electronic components from electrostatic discharge ESD damage wear an ESD wrist s...

Page 3: ...f 140 mm 5 51 in between the front rack posts and the front door A minimum of 950 mm 37 40 in between the front rack posts and the rear door M9000 AI E16 Height 843 mm 33 19 in Width 440 mm 17 32 in D...

Page 4: ...3 Figure 1 2 Airflow through the chassis M9000 AI E16 gateway Installation tools and accessories No installation tools are provided with the gateway Prepare them yourself as required...

Page 5: ...4 Figure 1 3 Installation tools Figure 1 4 Installation accessories...

Page 6: ...al cables Install cable management brackets Install fan trays Install power supplies Read safety guidelines Inspect the gateway Examine the installation site Prepare installation tools and accessories...

Page 7: ...four rack posts Table 2 1 Slide rail requirements Gateway model Max chassis weight full configuration Applicable slide rails Slide rail model Adjustment range Occupied space M9000 AI E8 87 4 kg 192 6...

Page 8: ...Removing the top hood Removing a fan tray 1 Wear an ESD wrist strap and make sure it is reliably grounded 2 Loosen the captive screws by using a Phillips screwdriver 3 Hold the fan tray handle and the...

Page 9: ...ents from being damaged because of short circuit As a best practice to lighten the chassis remove the fan trays from the chassis If you are not to remove the fan trays do not hold the handle of a fan...

Page 10: ...ge nut installation holes Figure 2 5 Marking cage nut installation holes M9000 AI E16 gateway 2 Install cage nuts in the marked square holes on the front rack posts Figure 2 6 Installing the cage nuts...

Page 11: ...doors first install the air filter doors and then install an air filter and a top hood on the M9000 AI E16 gateway Only the M9000 AI E16 gateway supports air filters and top hoods To install an air fi...

Page 12: ...ng the gateway 1 Unpack the grounding cable 2 Remove the grounding screws from the grounding holes at the rear of the chassis 3 Use grounding screws to attach the two hole grounding lug of the groundi...

Page 13: ...ve been installed on the two sides of an M9000 AI E8 gateway when the gateway is shipped You only need to attach the cable guides to the cable management bracket Installing cable management brackets f...

Page 14: ...t the right side The following installs a cable management brackets at the right side To install a cable management bracket 1 If any cable guide hinders installation of the cable management bracket pr...

Page 15: ...le management bracket Installing supervisor engine modules CAUTION The gateway supports active standby supervisor engine module SEM switchover when you install two SEMs for the gateway For the standby...

Page 16: ...hen push the SEM steadily into the slot along the guide rails 4 Rotate the handle downward Make sure the SEM makes close contact with the backplane 5 Fasten the captive screws on the SEM Figure 2 14 I...

Page 17: ...dily into the slot along the guide rails 4 Fully open the ejector levers of the SEM 5 Continue to push the SEM by its front panel until the ejector levers make close contact with the slot edges 6 Clos...

Page 18: ...00 AI E16 gateway provides four switching fabric module slots Only slots 10 and 11 are available for installing switching fabric modules You can install one switching fabric module or two switching fa...

Page 19: ...l the ejector levers make close contact with the slot edges 5 Close the ejector levers until the locking tabs lock the ejector levers in place Figure 2 17 Installing a switching fabric module for an M...

Page 20: ...rocedure is the same for installing an interface module or service module on an interface switch module The following procedure uses an interface module as an example To install an interface module on...

Page 21: ...s an example To install an interface switch module 1 Wear an ESD wrist strap and make sure the wrist strap is reliably grounded 2 Remove the filler panel from the target interface switch module slot s...

Page 22: ...rts 5 1 fan tray redundancy To install a fan tray in a slot in the upper row orient the fan tray with the LED at the bottom To install a fan tray in a slot in the lower row orient the fan tray with th...

Page 23: ...er supplies is greater than the system power consumption with a 20 power surplus as a best practice Provide a circuit breaker or fuse for power input of each DC power supply Make sure each input line...

Page 24: ...ot Then slide the power supply along the guide rails into the slot until the latch locks the power supply in place Figure 2 23 Installing a power supply M9000 AI E16 gateway Connecting a DC power cord...

Page 25: ...0 54A PSR3000 54A and PSR3000 54AHD AC power supplies are available for the gateway Table 2 3 Table 2 4 and Table 2 5 describe the specifications of PSR2400 54A PSR3000 54A and PSR3000 54AHD AC power...

Page 26: ...to 240 VAC 50 Hz 3000 W 240 VDC to 380 VDC 3000 W AC power supply configuration guidelines Determine the number of AC power supplies based on the system power consumption and the AC power supply confi...

Page 27: ...on an M9000 AI E16 gateway To install an AC power supply 1 Put your forefinger into the hole in the filler panel and pull out the filler panel along the guide rails Figure 2 25 Removing a filler panel...

Page 28: ...upply specifications HVDC power supply configuration guidelines Determine the number of HVDC power supplies based on the system power consumption and the HVDC power supply configuration based on the p...

Page 29: ...or To install a transceiver module and fiber cable 1 Wear an ESD wrist strap and make sure the wrist strap is reliably grounded 2 Remove the dust plug from the target fiber port 3 Pull the bail latch...

Page 30: ...O fiber connector Routing signal cables The cable management brackets are attached to the chassis front edges on its two sides As a best practice route the cables from the left half of the chassis thr...

Page 31: ...p the gateway clean and dust free No packing boxes packing bags or other packing materials left in the installation site Keep the air inlet and outlet vents of the gateway free of obstruction Gateway...

Page 32: ...the room before power on so you can quickly shut power off when an electrical accident occurs CAUTION Before powering on the gateway make sure all fan trays are present Power on check flow Figure 2 31...

Page 33: ...tware If the LED stays in this status the software version of the gateway does not match that of the module Flashing 0 5 Hz Off The module is operating correctly Flashing 0 5 Hz Flashing 0 25 Hz The t...

Page 34: ...are turned off The power cords are connected incorrectly The external power supply system is powered off Slot status LED SLOT Flashing green 4 Hz The module in the slot is loading software Steady gre...

Page 35: ...e M9000 AI E8 and M9000 AI E16 models The main components of the gateway include SEMs interface switch modules interface modules service modules switching fabric modules fan trays and power supplies C...

Page 36: ...switch module provides two slots for the installation of interface modules or service modules Power supply section No power supplies are provided with the gateway Purchase power supplies yourself Dete...

Page 37: ...36 M9000 AI E16 Figure 3 3 Front view 1 SEM section 2 Interface switch module AI security engine module section 3 Switching fabric module section...

Page 38: ...wo slots for installation of interface modules or service modules Switching fabric module section No switching fabric modules are provided with the gateway Purchase fabric modules yourself Only slots...

Page 39: ...module on the gateway Weights and dimensions The weight includes the chassis filler panels included and the packing materials Table 3 3 Chassis weights and dimensions Model Weight Height Width Depth...

Reviews: