39
x 1
3 sec.
x 1
3 sec.
x 1
3 sec.
Technical changes reserved
HTG410H
Devices installation and settings
7.1.3.6 To quit and save programming
Press button "PROG" for 3 seconds to exit the configuration level.
When the communication is established between the master and the
slave, the activity indicator "COM" is blinking on the display.
7.1.3.7 Function test for the electrical wiring connections
During testing, device SM103E must be supplied with current and
voltage to all connections. Testing requires a power factor of the
installation between 0.6 and 1. If the power factor of the installation
falls outside this range, the test cannot be performed. In the case of
4 BL / 3 BL / 2 BL / 1 BL only the connection of the current transformer
is tested. In the case of 4 NBL and 3 NBL the connection as a whole is
controlled.
Error
Error description
Err0
There is no error
Err 1 / 2 / 3
Reversed polarity of current transformer on phase 1 / phase 2 / phase 3
Err4
Reversed polarity of voltage between V1 and V2
Err5
Reversed polarity of voltage between V2 and V3
Err6
Reversed polarity of voltage between V3 and V1
7.1.3.7.1 Example of test operation without error
Press and hold button "Test" for at least 3 seconds to start testing
the connections. If, as shown in the example, no error is found,
press and hold button "Test" again for at least 3 seconds to return
to display mode.