24
Debugging and running
5.1 Confirm the project before running
◆
Unit power supply. Be sure to have the same power source as the product nameplate.
◆
The circuit connection of the unit. Check the wire diameter and wiring of the power supply wire, and
the ground wire is firmly connected. Check if the linkage of the pump or the like is properly
connected.
◆
Water pipes and pipes. Water pipes and pipes must be flushed at least two or three times to ensure
cleanliness without any contaminants.
◆
Check the water circulation system. Check that the water volume is sufficient, that the air is drained,
and that there is no leakage.
◆
When powering on for the first time or after a long time of shutdown, the power must be turned on in
advance to heat the crankcase for at least 2 hours.
◆
The water filter is installed in place as required, and there is no pollutant in the water filter.
◆
Water flow switch, the pump overload has been linked with the unit, and the drain valve has been
installed in place.
5.2 Check of running status
After the unit is running smoothly, check the following items:
number
Check item
Inspection essentials
Judging reference standard
1
Voltage
Voltmeter confirmation
±10% of rated voltage
2
Operating current of a single compressor
Galvanometer
confirmation
6
~
23A
3
Operating current of a single fan
Galvanometer
confirmation
0.2
~
3.6A
4
Unit inlet water temperature during cooling
operation
Thermometer confirmation
8
~
28
℃
5
Unit outlet water temperature during cooling
operation
Thermometer confirmation
5
~
21
℃
6
Unit inlet water temperature during heating
operation
Thermometer confirmation
24
~
50
℃
7
Unit outlet water temperature during heating
operation
Thermometer confirmation
29
~
55
℃
8
Inlet and out water temperature difference
Thermometer confirmation
2
~
8
℃
9
Compressor exhaust temperature
Thermometer confirmation
35
~
105
℃
10
Low pressure during cooling operation
Pressure gauge
confirmation
6.5
~
12.0bar
11
High pressure during cooling operation
Pressure gauge
confirmation
14
~
36.5bar
12
Low pressure during heating operation
Pressure gauge
confirmation
2
~
12.5bar
13
High pressure during heating operation
Pressure gauge
confirmation
18
~
36.5bar
14
Vibration, running sound
Auscultation or palpation
No abnormal vibration, running
sound
Remarks: The judgment reference standard is only the basis for the normal operation of the on-site unit.
The highest and lowest values of the reference standard are judged as the reference standard for the
maximum working condition and the minimum working condition of the unit. If the unit is stable and
exceeds the reference standard, please consult your local dealer and Haier for sale.
Summary of Contents for CA0065EANR
Page 8: ...5 1 2 Main components of the unit ...
Page 15: ...12 Installation 3 Diagram of arrangement of multiple chiller units Unit mm ...
Page 37: ......
Page 38: ......
Page 39: ......
Page 40: ......