Assembly
Information brochure · H-50.2 system components
V02R00 · 1134319 · 2022-11
32
5.13
Installation of a flexible rail connector
Flexible rail connector
Fig. 26: Installation of a flexible rail connector
Prerequisites:
A rung connector must be installed on the
rung above and below.
At least 5 rung clamps must be installed
below the flexible rail connector.
The flexible rail connector may not be in-
stalled on the first fall protection rail from
the bottom.
The ladder section on which a flexible rail
connector is used must be attached by at
least one ladder bracket (e.g. not a flange
transition piece).
Gap upon installation of the flexible rail
connector max. 0–1 mm.
The use of the flexible rail connector is recommended for long ladder routes (> 100 m) or towers
that sway significantly. Installation should be performed around half way along the access route.
1.
►
Insert the flexible rail connector into the fall protection rail from above.
2.
►
Apply the counterplate in a way that ensures it connected flush with the bottom fall pro-
tection rail, and screw both parts together.
⇨
The gap between the two fall protection rails must be kept as small as possible during
installation (0–1 mm) so that a maximum gap compensation of 4 mm is possible in
the event of fall protection rail fluctuation.