START UP CHECK LIST
1.1 Before putting any fan into initial operation, the manufacturer’s instructions should be followed.
Transportation, handling, and installation can cause fasteners to loosen, and cause misalignment
of fan components. Carefully follow this check list when commissioning equipment.
1.2 Lock out the primary and all secondary power sources.
1.3 A complete inspection should be made of all the ductwork and the interior of the fan. Make
certain there is no foreign material which can be drawn into or blown through the fan or ductwork
Appropriate protective measures and safety practices should be observed when entering or
working within these areas. These measures might include the use of goggles, respirators, or
other personal protective devices.
1.4 Make sure the foundation or mounting arrangement and the duct connections are adequately
designed and installed per drawings and in accordance with recognized acceptable engineering
practices and with the fan manufacturer’s recommendations.
1.5 Check and tighten all bolts, fasteners, and set screws as necessary .
1.6 Check the fan assembly and bearings for proper grounding to prevent static electricity discharge.
1.7 Ensure power and drive components such as motor starter, variable frequency drive, or hydraulic
power unit are properly sized, matched , and connected to the fan.
1.8 Check bearing for recommended lubricant and lubrication amount.
1.9 Spin the rotation assembly to determine whether it rotates freely, without hitting anything, and is
not grossly out of balance.
1.10 Inspect impeller for proper rotation for the fan design.
1.11 Check alignment of drives and all other components.
1.12 Check the belt drive for proper sheave selection and installation and make sure the sheaves are
not reversed (excessive speeds could develop).
1.13 Check for recommended belt tension.
1.14 Properly secure all safety guards.
1.15 Assure that all appropriate warnings have been put in place.