16
INSTALLATION
Before handing over the installation to the
customer it is a requirement under Document J the appliance is lit
and the functioning of the chimney system is checked for satisfactory
operation.
Be sure that the chimney is operating and ALL smoke and fumes are
vented to the atmosphere through the chimney
terminal.
Check all joints and seals.
Clean the outside of the appliance to
prevent any stains becoming burnt on.
Check the flue draught which should read 1 - 2mm, or 0.1 - 0.2 mbar.
If Building Control Consent route is being sought please complete the
check list on page 17.
For a registered Competent Persons Scheme, such as HETAS, please
complete the Certificate Of Compliance, which is used for checking
and reporting the installation, as imposed by the Government
Explain the controls and operation of the appliance to the customer.
The above details
must
be checked and the Building Control Checklist on page 17
completed in full by the installer at the time of the installation
Please answer all questions as fully as possible. Hamlet
stoves
cannot be held
responsible for the chimney or the installation of the stove.
FINAL CHECK
Hamlet Camborne Deluxe Stoves