ceiling motor
6.5. Charging the batteries
Place the ceiling motor on the charging pins on a regular basis, at least
once every 2 days.
Overcharging is not possible.
If the Ceiling Motor emits a beep and/or the battery LED on the Con-
trol Panel is blue, it needs to be charged immediately.
The signal means that the battery can function for one lifting cycle only.
■
Put the ceiling motor on the charging pins. The battery LED on the
Control Panel is orange. If the batteries are fully charged, the LED
will switch off after 60 seconds.
■
Do not use the ceiling motor while charging.
■
The indicator light of the chargers shows the following functions:
• Orange: the batteries are being charged
• Green: the batteries are fully charged
6.6. Automatically stopping the Ceiling Motor at a specified
location.
This position is only possible on types 2810 L and HM 2815 L IR and
acts as an aid for stopping at a specified location. If you do not use this
function, then you have to position the motor in the correct location
yourself.
Fasten the magnet to the rail in the position where you would like to
stop. For example: to stop above the toilet, bed, bath, or any other pre-
ferred location. The charging pins come standard with this functionality.
6.7. IR handcontrol
6.7.1. Battery warning IR handcontrol
The IR handcontrol has a built-in battery warning in the event of low battery voltage. An alarm consisting of one
long beep and three short beeps will sound twice. This will go off approximately 10 seconds after the transmitter
was last used. Replace the batteries as soon as possible. See 9.5
6.7.2. Cleaning
The IR handcontrol can be cleaned using a damp cotton cloth and alcohol, chlorhexidine or ethyl alcohol.