INITIAL ATTACHMENT TO TRACTOR
The machine will be delivered in a partially dismantled condition, secured with transport
strap and banding.
Choose a
firm level site
.
Remove the transport strap, banding
straps and loose items.
Raise the machine using overhead
lifting equipment with a minimum
capacity of 1500kg SWL.
LEAVE IN POSITION AT THIS STAGE.
Lower the legs and pin in position
selecting the holes that position the
machines gearbox stub shaft approx.
75 mm below the tractors P.T.O. shaft.
Note: Leg pin position used.
Unbolt stabiliser from machine and
remove the stabiliser nose quadrant pin.
Locate axle-mounting arms onto the mainframe and secure in position using the correct
nuts and bolts supplied, tighten nuts when correct hole location has been selected -
see