Operating Manual
for HMG gasburner
Hansa burners are quality products. Expert installation, regulation/adjustment and servicing/maintenance
provided, our burners will work safely, reliably and economically for many years.
Before the assembly of the burner
the following steps have to be carried out:
Installation and Commissioning
This burner has to be installed and commissioned only by an expert. Therefore locally valid rules and
guidelines are to be strictly observed. He will bear responsibility for the appropriate laying out.
Norms
The following norms have to be considered for safe, environment-friendly and energy-saving running:
DIN
4756
gas firing units, DIN 4788 part 2 gas burner with fan ventilation, DIN 4789 connection of atomizing
oil- and gasburner with fan ventilation on heat generators, VDE 0116 elektrical equipment of firing plants.
- Check, whether the heat generator is impermeable on its smoke gas side.
- In case of second hand heat generators the heating surfaces have to be clean in order
to achieve a good degree of effectiveness.
- Gas pipes have to be laid professionally and must be absolutely impermeable.
Content of box:
1 Gasburner HMG
2 Fixing screws M8
1 Operating-Manual
mit 2 underlay discs
1 Flange gasket
1 Gasvalve
1 Plug with 7 poles
1 Conic case fixing screw
Assembly:
First you take the burner out of its box and dismantle the burner's bonnet.
Then you loosen the 4 outer screws of the burner case and take the upper part out of the lower part.
Now you fix the lower part to the boiler by means of the flange gasket (pic.1). Fit the upper part to the
lower part again and tighten the four outer screws. Now you assemble the gas valve, the gasket of
which you will also find in the transparent pack. Finally
assemble the gas supply to the gas valve. If gas supply and
electrical connection (euro-plug with 7 poles) is established, the
burner is operational. Please pay attention to the remark relating
to the air blockade on page 5.
Picture1 flange gasket
LK=150
L = 81mm
F = 8,5
page 2 of 5