6 - Maintenance
36
Vertical Alignment of Middle and Outer Sections
Steps for adjustment:
1.
Start with the middle section, which is aligned with the inner
section.
2.
At the top of the boom, nuts (A, B) are adjusted. Wrench = 41 mm.
Raise the boom: Loosen (A), tighten (B).
Lower the boom: Loosen (B), tighten (A).
3.
At the bottom of the boom, the ram eye (C) can be adjusted if
needed. Remove the black pin (D), loosen the jam nut (E) and turn
the ram eye 180°. Replace the black pin and check alignment of the
boom section.
4.
When the middle section is aligned, tighten all jam nuts.
Adjustment is completed when the alignment is straight, and the
folding is trouble-free.
5.
The outer section is aligned with the middle section in the same
way by completing steps 2 & 4.
Summary of Contents for Delta Force Boom
Page 2: ......
Page 4: ......
Page 8: ...1 Welcome 6 ...
Page 12: ...2 Safety notes 10 ...
Page 18: ...3 Description 16 ...
Page 20: ...4 Sprayer setup 18 ...
Page 24: ...5 Operation 22 ...
Page 47: ...45 Diagrams Boom Hydraulics 2 Fold Boom Mechanical Yaw 8 Technical specifications ...
Page 48: ...8 Technical specifications 46 Hydraulic Yaw ...
Page 49: ...8 Technical specifications 47 Mechanical Yaw with Norac ...
Page 50: ...8 Technical specifications 48 Hydraulic Yaw with Norac p ...
Page 51: ...8 Technical specifications 49 Boom Hydraulics 3 Fold Boom Hydraulic Yaw ...
Page 52: ...8 Technical specifications 50 Hydraulic Yaw with Norac ...
Page 55: ......