38
HARDI
®
EAGLE 3PT BOOM OPERATORS MANUAL
6.7 Adjusting Wings Level To Ground
With boom unfolded (in the spraying position), check that boom sections
are parallel to center frame and level to the ground. Adjust, if necessary,
as detailed below.
A) HY Booms
1. Loosen jam nut (
A
)(Fig.17).
2. Adjust nut (
B
)(Fig.17) in or out until wing is level to ground.
3. Secure jam nut (
A
)(Fig.17).
Same procedure applies to both sides.
Fig. 17
Fig. 18
C) HZ and HT Booms
1. Ensure cylinder is fully extended.
2. Loosen jam nut (
A
)(Fig.18).
3. Apply an adjustable wrench to
the machined surface at
(
B
)(Fig.18).
4. Turn the cylinder rod until boom
is level to the ground.
5. Secure jam nut (
A
)(Fig.18).
Same procedure applies to both
sides.