II
HARGASSNER Heating technology for
Biomass
A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 office@hargassner.at
7
Safety regulations
Chapter
II: Safety regulations
1
General safety advices
1.1
Obligation to instruct, external personnel, children
Work on electrical parts of the boiler may only be carried out by an electrician and
in compliance with the electro-technical rules and standards.
Work on hydraulic systems may only be carried out by personnel with specialised
knowledge and experience in heating engineering and pipework construction.
1.2
Special measures prior commissioning through the operator
• Licensing requirements for safe operation and accident prevention regulations
must be observed!
• Do execute verifications prior first start up.
See „Checks prior commissioning“ on page 12.
• Do execute verifications prior commissioning.
See „Inspections prior starting up the boiler“ on page 13.
D A N G E R
Risk of death, injuries, damage from inappropriate installation
• Observe the safety instructions of the boiler and in the operation manual!
• Read the user manual PRIOR to commissioning.
In the cladding door is a storage compartment
Incorrect actions by unauthorized individuals
• Works on the boiler through qualified and experienced personnel only.
• Decide who is responsible for managing the boiler.
• Keep external, unauthorised and untrained people away from the boiler and the fuel
storage room
• No transfer of control entry codes
• Observe legal minimum age of personnel.
• Place prohibition sign in front of boiler room door and fuel storage door.
Risk of suffocation due to odourless carbon monoxide
• Ventilate sufficiently before entering the fuel storage room
• Keep window/door open during stay
• Always have a second person outside to supervise.
Summary of Contents for Classic 12
Page 64: ......