MODU-FIRE
®
Forced Draft Gas-Fired Boiler 2500-3000
9
3.1.2
Storage Prior to Installation
If the boiler is not installed immediately, it must be stored in a location adequately protected from the weather,
preferably indoors. If this is not possible, then it should remain in the shipping container and be covered by a
tarpaulin or other waterproof covering.
NOTICE!
Controls and other equipment that are damaged or fail due to weather exposure are not covered by
warranty.
3.2 C
OMPLIANCE WITH
C
ODES
The
MODU-FIRE
®
Forced Draft
boiler with standard components and many options complies with American
National Standard/CSA Standard ANSI Z21.13/CSA 4.9, latest edition. The heat exchanger is constructed and
stamped in accordance with ASME Boiler and Pressure Vessel Code, Section IV for 160 psig maximum operating
pressure and 250º F maximum operating temperature. Other codes or approvals which apply will be labeled on
the boiler.
Installation of the boiler must conform to all the requirements of all national, state and local codes established by
the authorities having jurisdiction or, in the absence of such requirements, in the U.S. to the National Fuel Gas
Code, NFPA 54/ANSI Z223.1., latest edition, and the specific instructions in this manual. In Canada, the
equipment shall be installed in accordance with the current Installation Code for Gas Burning Appliances and
Equipment, CAN/CSA-B149.1, and applicable Provincial Regulations for the class which should be carefully
followed in all cases. Authorities having jurisdiction should be consulted before installations are made.
Where required by local codes, the installation must conform to American Society of Mechanical Engineers Safety
Code for Controls and Safety Devices for Automatically Fired Boilers (ASME CSD-1).
In the Commonwealth of Massachusetts, see Massachusetts Installation & Owner’s Manual Supplement.
3.3 S
ETUP
3.3.1 Foundation
Provide a firm, level foundation, preferably of concrete.
NOTICE!
The boiler may be installed on a combustible floor; however, the boiler must
never
be installed on
carpeting.
NOTICE! This boiler is certified for
indoor
installation only.
3.3.2 Placement
The boiler must be level and upright to function properly. Use shims or other approved structural devices to
properly level boiler.
NOTICE! Note any damage, suspected potential damage, or shortage of materials on the freight bill
and immediately notify the carrier. File all claims for shortage or damage with the carrier. Claims for
hidden damages must be filed with your carrier within 7 days. The boiler carton is equipped with a
“Tip (N) Tell”. If "Tip (N) Tell” arrow point is blue, that indicates that the package has been on its
side or tipped over in transit.
Summary of Contents for 1004905923
Page 2: ...MODU FIRE Forced Draft Gas Fired Boiler 2500 3000 2 ...
Page 45: ...MODU FIRE Forced Draft Gas Fired Boiler 2500 3000 45 6 1 3 Wiring Schematic ...
Page 48: ...MODU FIRE Forced Draft Gas Fired Boiler 2500 3000 48 6 1 6 Rear Junction Box ...
Page 49: ...MODU FIRE Forced Draft Gas Fired Boiler 2500 3000 49 6 1 7 Customer Connections ...
Page 56: ...MODU FIRE Forced Draft Gas Fired Boiler 2500 3000 56 ...