MACH® Series
Gas-Fired Boiler
Installation
24
3.8 P
RE
-S
TART
C
HECK
L
IST
Before attempting to start the boiler, make sure the following items have been completed.
1. Inspect the gas train, blower, ignition electrode and boiler in general to be sure there was no damage during
shipment or installation.
2. Flue gas from the boiler is properly vented; (refer to Section 3.5)
3. Gas connection has been made, pressure tested for leakage and the line purged of air. Make sure all required
vents have been installed. (refer to Section 3.6)
4. Water connections are complete and the boiler and system have been filled and purged of air. (refer to Section
3.7)
5. The boiler is connected to a 120 volt power source with a disconnect having adequate overload protection. (refer
to Section 3.4)
6. Combustion air openings are not obstructed in any way and have adequate capacity. (refer to Section 3.5)
7. The boiler is placed the proper distance from any combustible walls (refer to Section 3.3.3).
8. Relief valves have been piped to an acceptable drain. (refer to Section 3.7)
9. Condensate piping is properly connected. (refer to Section 3.7)
10. Verify system water quality is within specifications. (refer to Appendix B)
3.9 S
AFETY
C
HECKS
The following checks of safety systems must be made before putting the boiler into normal operation.
Before firing the boiler refer to Section 4 for information on the use of the controls, lighting, and shut-down
procedures.
NOTICE!
If the piping system attached to this unit will be chemically cleaned, the boiler must be disconnected
from the system and a bypass installed so that the chemical cleaning solution does not circulate through the boiler.
Following chemical cleaning, the system should be thoroughly rinsed to remove cleaning agents prior to
reconnecting the boiler to the system.
NOTICE!
Glycol and other additives must be approved for use in aluminum boilers and must meet the
requirements listed in Appendix B to prevent damaging the boiler.
NOTICE!
Under no circumstances should petroleum based cleaning or sealing compounds be used in the boiler
system.
NOTICE!
Chemicals added to the system must be approved by the chemical manufacturer for use in aluminum
boilers.
NOTICE!
Under no circumstances should the hydronic system be flushed while the boiler is attached to the
system since the debris or corrosion products could accumulate in the boiler and plug the boiler heat exchanger.