2.6.2 Piping Line Flush
1.
Close isolation valves on R1600 (as shown in Figure 2.9 below).
Remove protective cap from flush valves and connect hose to each of the ¾” GHT
(Garden Hose Thread) connections (as shown in Figure 2.10).
A ¾” female-to-female GHT adapter, if needed, has been
included in the Preventative Maintenance (PM) Test Kit
provided separately to the Installer.
Figure 2.9 Valve Close
Figure 2.9 Valve Close
Figure 2.9 Valve Close
Figure 2.9 Valve Close----ups (All Valves Illustrated in the CLOSED Position)
ups (All Valves Illustrated in the CLOSED Position)
ups (All Valves Illustrated in the CLOSED Position)
ups (All Valves Illustrated in the CLOSED Position)
Supply
Side
Isolation
Valve
Supply
Side
Flush
Valve
Return
Side Flush
Valve
Return
Side
Isolation