Haskris Model R1600 No Load Start-Up Checklist
Copyright © 2011 Haskris Company
39
www.haskris.com
Version R1600-X-R407C-XXX Instruction Manual Rev00
No Load Start
No Load Start
No Load Start
No Load Start----Up
Up
Up
Up Checklist for Haskris
Checklist for Haskris
Checklist for Haskris
Checklist for Haskris R1600, S/N HL
R1600, S/N HL
R1600, S/N HL
R1600, S/N HL ____________
____________
____________
____________
Project Name ______________________________ Location ___________________________________
Note:
Note:
Note:
Note: Checklist to be completed by Haskris Approved Service Agent. Checklist MUST be completed for “Full
Load” Start-up to be scheduled.
Directions:
Directions:
Directions:
Directions:
Fax both pages of completed checklist to Haskris (Fax#: 847-956-6595)
Pre Start
Pre Start
Pre Start
Pre Start----Up
Up
Up
Up Checklist:
Checklist:
Checklist:
Checklist:
___
Unit is securely mounted and level.
___
No Refrigeration Service Contactor labels have been affixed to the interior or exterior of the R1600.
___ Clearances for service, ventilation, and access to control panel are adequate per R1600 Instruction Manual.
___ Electrical service to R1600 per table below (Record Inlet Voltage and Branch Circuit Rating):
___
Confirm compressor crankcase heater has been energized for a minimum of 12 hours. (See Section 3.1)
___
Confirm proper phase by verifying the red ‘FAULT’ LED is not lit on phase monitor. (See Section 2.5.1)
___ Hard copper piping with vents/drains as required and properly supported.
___ Vibration Isolators installed at R1600 on both glycol supply and return lines.
___ Separately fused heat trace covered with suitable thickness of closed-cell, UV resistant insulation on all piping
exposed to low ambient temperatures, as required.
___ Supply/Return lines labeled over insulation.
___ 12’ long loop of 1-1/2” reinforced opaque hose between supply and return outlet in equipment room provided.
___ Supply and return ball valves provided at indoor WW4.
___ Supply side temperature (0-100°F) and pressure (0-100psig) gauges provided at indoor heat exchanger.
___ Return side temperature (0-100°F) and flow (10-50gpm) gauges provided at indoor heat exchanger.
___ Leak check performed and no leaks in external piping loop per R1600 Instruction Manual.
___ Preventative Maintenance (PM) Test Kit has been provided to Start-Up Agent.
___ System (50 gallon tank and entire piping loop) is filled with gallons of glycol/distilled water solution.
___ Reservoir is at tank full level.
___ Lines air purged per R1600 Instruction Manual.
___ Glycol solution % (Record actual measurement here).
___ Glycol solution pH level (Record actual measurement here).
___
Spare glycol manufacturer______________________Glycol type__________________________
___ Installer has provided an additional 10 gallons of propylene glycol/distilled water (35% by volume) to top off
system when no-load start-up is performed.
___ Confirm all isolation valves are open and all flush valves are closed.
Note:
Note:
Note:
Note: If any of the above items are found to be deficiencies, DO NOT CONTINUE WITH START-UP and
notify Haskris immediately. Installer will issue a Credit Card Purchase Order to Haskris Start-Up Agent if any
items are found incomplete and resulting in delay of system start-up. If no deficiencies are found, continue
with Start-Up Checklist below.
--Page 1 of 3—
(continued on next page)
Nominal Power:
Nominal Power:
Nominal Power:
Nominal Power: 480V-3Ø-60Hz,+5% / -10% MCA: 54.3A, MOCP 70A
Record Voltage at
Disconnect
(V)
L1-L2
Confirm and Record Size of Time Delay
Breaker (Fusing) Supplying Chiller
(A)
L2-L3
L1-L3
!
!