82
4000827180
E 09.18
USA / GB
D
- Operation instructions
HA12CJ - HA32CJ - -
5.6 - L
IFTING
OPERATION
During loading / unloading operation with an overhead crane, it is important to respect the
following :
• Put the machine in stowed position, boom and arm fully retracted and lowered.
• Platform must be empty.
• Rotate the turret and the jib to the configuration in the photos below.
• Verify that lifting accessories are in good operating condition and match the technical
specifications. Lifting devices must be attached only to the designated lifting eyes.
• Each of the slings used for lifting the machine must be adjusted to keep the machine level
and to minimize the risk of damage to the machine.
• Anchorage point for lifting are identified / labeled by the following symbol
.
• ONLY trained and authorized personnel should attempt to lift the machine.
L i f t i n g c o n f i g u r a t i o n w i t h s l i n g s
Never lift the machine with slings attached to counterweight.
Machine
Distance C
Number of slings
Length A
Length B
Maximum load per sling
and shackle
HA12CJ/CJ+
HA32CJ/CJ+
20 cm (8 in)
4
5 m (16 ft 5 in)
5 m (16 ft 5 in)
5000 DaN (11241 lbf)
Before using slings, lift the jib to obtain a minimum 20 cm (8in) clearance between the ground and cage.
A
B
C
Summary of Contents for HA12CJ
Page 2: ...2 4000827180 E 09 18 USA GB HA12CJ HA32CJ HA12CJ HA32CJ ...
Page 84: ...84 4000827180 E 09 18 USA GB D Operation instructions HA12CJ HA32CJ HA12CJ HA32CJ Notes ...
Page 94: ...94 4000827180 E 09 18 USA GB E General Specifications HA12CJ HA32CJ HA12CJ HA32CJ Notes ...
Page 106: ...106 4000827180 E 09 18 USA GB G Other information HA12CJ HA32CJ HA12CJ HA32CJ Notes ...