48
WE2110
HBM
A2181-1.0 de/en
4
Installation
4.1 Start-up of WE2110
The following steps must be followed to install the indicator:
1. First inspect the unit to ensure it is in good condition and all the required
options are installed, and all the connectors required are available.
2. Use the connection diagrams (from page 11) to wire up the unit to the load
cells, power and other external devices.
3. Follow the “Setting Up the WE2110” flowchart on the next page, to digitally
set the unit (the section following the flow chart provides additional notes on
the steps involved).
4. Refer to the calibration flowchart for the zero and span calibration steps and
if necessary for the linearisation (see page 8).
5. The unit can then be sealed for security if necessary.
4.2 First steps with WE2110
•
Connect the load cells and other devices
•
Press the hidden setup key with a pencil
•
Wait until BUILD is displayed
•
Select the scale type
<BUILD> <TYPE>
(Items: SINGLE range, DUAL range, DUAL Interval, DIRECT mV/V)
•
Enter decimal point
<BUILD> <DP>
•
Enter scale capacity 1
<BUILD> <CAP1>
•
Enter verification interval e1
<BUILD> <E1>
(Only valid: 1, 2, 5, 10, 20, 50, 100)
•
Enter scale capacity 2
<BUILD> <CAP2>
(if dual range/interval selected)
•
Enter verification interval e2
<BUILD> <E2>
(if dual range/interval selected)
•
Select Additive Tare value
<BUILD> <AD.TARE>
•
Select unit
<BUILD> <UNITS>
•
Go to the CAL menu with the SELECT GROUP Key
Summary of Contents for WE2110
Page 2: ...Deutsch Seite 3 36 English Page 37 70...
Page 36: ...36 WE2110 HBM A2181 1 0 de en...
Page 70: ...70 WE2110 HBM A2181 1 0 de en...
Page 71: ......