6 Using the heating system – Performing a chimney sweep measurement
80
P
ROCEDURE
FOR
FILLING
WITH
PELLETS
1.
Switch the heating system off.
✎
See the “HDG Control” operating manual, chapter “5 Using the
control unit”, section “5.3 Switching off the heating system”.
✓
The heating system is now switched off.
2.
Double check that the heating system is switched off and wait for
burn out to finish.
3.
Inform the tanker driver that the pellet storage room can be filled.
4.
After filling is completed, close the injection and extraction noz-
zles.
5.
Re-starting the heating system.
✎
See the “HDG Control” operating manual, chapter “5 Using the
control unit”, section “5.2 Switching on the heating system”.
✓
The filling of the pellet storage is completed.
6.3 Performing a chimney sweep measurement
✎
See the “HDG Control” operating manual, chapter “5 Using the
control unit”, section “5.8 Performing a chimney sweep measure-
ment”.
6.4 Switching off the heating system for repair
work
1.
Switch the heating system off.
✎
See the “HDG Control” operating manual, chapter “5 Using the
control unit”, section “5.3 Switching off the heating system”.
2.
Allow the fire in the boiler to burn out and cool off.
3.
Turn off the main switch.
✓
The heating system is switched off and without current.
Important!
Frost danger
Only completely shut off the power to the heating system if the
danger of frost can be ruled out.
There is still electrical voltage in the system.