5 Commissioning the system – Procedure
78
E
LECTRICAL
CONNECTIONS
•
All the sensors and actuators are correctly connected and properly
plugged in to the module.
•
The mains supply is correctly connected.
•
The cables between the control unit, central module and drive
module or to the expansion modules are attached properly.
•
Any unused inputs are bypassed.
5.2 Procedure
✎
See also operating manual “HDG Control”, Chapter “4 Commis-
sioning the system”.
Danger!
Dangerous electrical current or voltage
Isolate the mains cable to the heating system.
Important!
Commission the HDG Compact 25 - 80 heating system in accord-
ance with the specifications from the supplied commissioning pro-
tocol.
Caution!
Damage from smoke
If the ash necks are empty or the ash containers are not at least half-
filled when commissioning or re-starting after cleaning, there is a
danger of smoke coming from the boiler.
Make sure that both ash containers or the ash necks are at least half-
filled with ash or sand.