5 Commissioning the system – Requirements
41
5 Commissioning the system
The heating system is initially commissioned by specialists from HDG
Bavaria or from an authorised HDG partner.
Commissioning includes an introduction to the operation and
maintenance of the heating system as well as measurements to
determine exhaust emissions and combustion performance.
5.1 Requirements
The following requirements must be met to ensure there are no
problems during commissioning.
•
The boiler is installed properly.
•
The heating system has been filled with water as specified.
•
The heating system has been bled.
•
The pressure of the membrane expansion vessel has been
adapted to on-site conditions.
•
All required DIN EN 12828 safety devices have been installed and
are ready for operation.
•
The power supply to all components is ensured. (Makeshift
solutions are not sufficient!)
•
The chimney installation corresponds to the legal regulations.
•
All doors and openings on the boiler and on the chimney
connection pipe have been checked for a proper seal.
•
Air supply for combustion has been provided.
•
A sufficient amount of fuel is available.
5.2 Procedure
✎
See the “HDG Control” operating manual, chapter
“Commissioning the system”.
Danger!
Material damage and injury due to incorrect commissioning
Commissioning the system requires comprehensive expertise. If
this commissioning is done by an untrained person, the heating
system could be damaged.
Only allow authorised specialists to perform the commissioning.