4 Planning and installation – Installing the heating system
51
I
NSTALLING
THE
CONTROL
CABINET
1.
Remove the cover plate of the control cabinet.
2.
Bolt the control cabinet (1) firmly to the stud bolt (4) on the boiler
using a 13 mm spanner.
3.
Insert the green and yellow earth cable (2) against the upper right
stud bolt (3) and screw it tight.
✓
The control cabinet has been installed.
A
TTACHING
THE
BOILER
CLADDING
F
RONT
BOILER
CLADDING
1.
Remove the pre-mounted flat-headed screws of the front
cladding (2) from the boiler body.
Figure 4/23 - Installing the control cabinet
2
4
3
1
Figure 4/24 - Attaching the front boiler cladding
1
2