4 Planning and installation – Pellet bunker
69
H
YDRAULIC
SYSTEMS
✎
The available hydraulic systems can be found in section “4.10 HDG
hydraulic systems” in this chapter.
4.6 Pellet bunker
I
NSTALLING
THE
INJECTION
AND
EXTRACTION
NOZZLES
1.
Push the injection nozzle (1) into the hole through the wall (2).
2.
Cement the injection nozzle in place with mortar or inject the
cavity around the nozzle with expanding foam which is suitable
for the on-site conditions.
3.
Earth the injection nozzle.
4.
Install the extraction nozzle as just described.
5.
Earth the extraction nozzle.
✓
The injection and extraction nozzles have been installed.
Danger!
Dust explosion due to build up of static charge!
Only qualified electricians certified according to TRBS 1203-1 may
perform work on electrical systems in areas at risk of explosion.
On the connecting pipes, there should not be any protruding
interior edges or weld beads. Otherwise, the pellets would be
damaged at these points when blown in.
Figure 4/57 - Installing the injection and extraction nozzles
1
2
Summary of Contents for Pelletmaster 15
Page 1: ...hdg bavaria com HDG Pelletmaster 15 25 Operation Manual V 03 08 2008 ...
Page 2: ......
Page 170: ...170 HDG Pelletmaster 15 25 V 03 en HDG Bavaria GmbH 08 2008 ...
Page 171: ......