1. Install the 4” inner collar by first
placing the 4” x 6” gasket ring onto
the base of the collar. Install the
collar and gasket to the stove using 8
of the screws provided.
2. Install the outer collar in similar
fashion using the larger gasket ring
and the remaining 8 screws.
3. Install the 45º elbow over the outer
collar. Place the elbow so that the
twist lock end is pointing up.
4. Install one of the 9” pipe sections
into the elbow by fully inserting it
and turning approximately ¼ turn
clockwise, until the 2 sections are
fully locked. Install the 90º elbow in
similar fashion.
5. Move the stove and pipe assembly
back until the 90º elbow is flush to
the wall. The 9” vertical pipe should
be parallel to the wall. Draw a circle
around the pipe. Use the center of
this circle as the center point of the
10” x 10” square wall pass through.
(It should be approximately 40-1/4”
above the floor) Cut and frame the
wall pass through.
6. Place the interior wall thimble into
the 10” x 10” wall pass through.
Secure it with 4 screws (not
provided). Install the exterior portion
of the thimble in similar fashion,
overlapping the 2 sections.
›
Caution:
For building with vinyl siding,
a vinyl siding standoff should be
installed between the vent cap and the
exterior wall. Refer to venting
manufacturer’s Instructions for Direct
Vent Heaters for installation instructions.
7. Install the horizontal vent
termination on the outside of the
wall. Make sure both of the retaining
straps extend through interior wall
thimble. Before attaching the vent
termination to the outside of the
house, run a bead of non-hardening
mastic around its’ outside edges, so
as to make a seal between it and the
wall. The arrow on the end cap
should point up. Secure the cap to
the wall with the appropriate screws.
8. Place the thimble cover onto the 90º
elbow. Put the 9” pipe into the
horizontal vent cap, (the vent pipe
must extend into the horizontal vent
cap a minimum of 1-1/4”). Move the
stove and vent pipe into position,
insert the 9” pipe into the 90º elbow
and twist to lock it. Secure the straps
from the horizontal vent termination
to the interior pipe with 2 sheet metal
screws, keeping screws close to wall
thimble as possible. Bend or cut the
excess strapping so that the thimble
cover will fit properly. Screw the
thimble cover to the wall.