26
Heat-Timer Corp.
First-On/First-Off (FOFO)
(AVAILABLE IN PID CONTROL MODE ONLY)
• If First-On/First-Off (FOFO) is selected, the concept will follow this example; if A is the lead, the starting sequence of boilers will
be A, B, then C. When the de-energizing of the stages starts, it will turn off A, B, Then C. Then, stage D will be the new lead for
the next load.
Boiler Operation Mode
Auto, Standby, Off, On
Default: Auto
BOILER (Button)
By pressing the
BOILER
button, the Boiler Operation mode menu selection will display.
There are four modes. By pressing the
BOILER
,
NEXT
, or
PREV
buttons the display
will scroll between the different modes.
---- BOILER AB ----
Auto
Standby
Off
On
•
Auto
-
In this mode boiler stage will operate based on control settings. Boiler can be used in rotation. The status will read:
◦
---
(All stages are Off)
◦
LOW
(Only lowest firing stage on a multi-stage boiler is On)
◦
MED
(Both Low and Medium firing stages on a 3-stage boiler are On)
◦
MLOW
(Both Low and Medium Low firing stages on a 4-stage boiler are On)
◦
MHIGH
(The three lowest firing stages on a 4-stage boiler are On)
◦
HI
(The On/Off boiler stage is On)
◦
HIGH
(All firing stages on a multi-stage boiler are On)
•
Standby
- Boiler will start only after all Boilers set to Auto are on for the full Standby Delay. The display status will read
STB
.
•
Off
-
Boiler relay will be Off until this setting is changed. The display status will read
OFF
.
•
On
-
Boiler relay as well as System relay will be On until this setting is changed. The display status will read
ON
.
• The following are the possible stage status:
◦
C/E
- Will only occur to a boiler wired to an extension and the Extension communication has terminated.
◦
L/O
- The boiler is in lockout due to lockout input is shorted on the Extension.
Schedules
SELECT
Setting//Schedules
• The MPCQ Platinum has two levels of heat. The Day Time level is used when a
building is occupied and people are active.
• The Night Time (Setback) level is used when a building is not occupied, or when
people are sleeping.
• The MPCQ Platinum can have up to four Day Time and four Night Time (Save)
periods for each individual day of the week. The MPCQ Platinum will show which
period is being edited on the 2nd line of the display.
• Every time the MPCQ Platinum updates the clock time, it checks the Day/Night
program. If there is a matching Day/Night time programmed, it sets the heat level
accordingly, otherwise, the heat level is not changed.
• If an office building is unoccupied all weekend, simply set the last Night setting (8:00
PM on Friday). Then, set all the Saturday and Sunday programs to **:**
(using the
DEL button). The control will stay in Night Time (Save) until it reaches a Day setting
(6:00AM on Monday).
----- SCHEDULES -----
Day/Night Schedule
Copy Schedule
Set Date/Time
ALERT
The MPCQ Platinum will ignore any
Time setting that reads **:**.
The Day #1 setting for any Day
Time is used by the Boost. The last
Night Time setting is used by the
Early Shutdown ESD.
Day/Night Schedule
Day#1, Day#2, Day#3, and Day#4
Day #1 default: 6:00 am
Night#1, Night#2, Night#3, and Night#4
Night #1 default: 10:00 PM
SELECT:
Settings/Schedules/Day Night Schedule
• Use this setting to set up to 4 Day Time and 4 Night Time (Save) settings per each day
of the week. The Day Time settings allows the MPCQ Platinum to cycle based on
the Day Outdoor Cutoff, Day Heat Adjustment, and Day Space Target (when Cycle
is selected as the Operation Mode) or based on the Set point and Day Outdoor Cutoff
(when Set Point is selected as a Operation Mode). See Operation Mode on page 17.
------ SCHEDULES ------
MON # 1
Day Time
6:00Am
Night Time 10:00Pm