1. Mount the column including the bottom 

flange on the rod unit as illustrated. 
Column needs to be turned so that the 

square tube faces true south in the northern 

hemisphere or true north in the southern 

hemisphere. To do so follow these steps:
2. Launch the compass app on your smart 

phone. This compass is GPS compensated, 

making it more accurate than a regular 

compass.
3. Align the phone to true south (or north) 

according to the compass.
4. Rotate the column so that the edge of the 

tube lines up with the edge of the phone. 

Make sure the compass is not distorted by 

being too close to any metal objects.
This alignment can be fine-tuned after the 

installation is complete and the tracker has 

turned towards the sun.

 

4

5. Adjust bottom nuts to 

horizontally align the column's 

upper flange using a spirit 

level.
6. Tighten top nuts and then 

bottom nuts to secure the 

column.

South

Summary of Contents for HELIOMOTION PV-4

Page 1: ...QUICK ASSEMBLY GUIDE PV 4 HELIOMOTION HelioZenit Revision 1 2021...

Page 2: ...1x 1x PART I FOUNDATION...

Page 3: ...should be at least 70x70 cm 80 cm deep 400 liter Push the rod unit into center of the concrete and let the flange rest on top of the concrete Use a spirit level to align the flange horizontally Allow...

Page 4: ...template Make the holes 20 mm wide and 250 mm deep Use compressed air to remove any debris and water from the holes to ensure a clean bonding surface Fill the holes 2 3 full with chemical anchor adhes...

Page 5: ...accurate than a regular compass 3 Align the phone to true south or north according to the compass 4 Rotate the column so that the edge of the tube lines up with the edge of the phone Make sure the co...

Page 6: ...1x 1x 6x 4x PART II TRACKER...

Page 7: ...6x 4x 1x 1x 1 2...

Page 8: ...2x 1x 1x 20x 2x 4x 1x 2x 4x 2x PART III FRAMEWORK...

Page 9: ...2300mm 2000mm 150mm 150mm 2x 2x 4x 2 1...

Page 10: ...2x 960mm 960mm 2x 45mm 45mm 4 3...

Page 11: ...592mm 592mm 1x 1x 4x 1 2 1x 5 6...

Page 12: ...16x 45mm 600mm 45mm 600mm 600mm 600mm 1324mm X X 4x 8 7 X Panel width 2 1324 2...

Page 13: ...4x 10x 10x 16x PART IV PANELS...

Page 14: ...th four panel clamps C Remove the extension rod and attach only the black angle rod Make sure to prevent the panels from swinging downwards when changing the rod Leave both fork joints F and one of th...

Page 15: ...n Standard applications are listed below String inverter Grid tied string inverters generally supports a high voltage PV input Therefore all 4 panels are typically connected in series when using a str...

Page 16: ...C U must be connected by a certified electrician However preparation work may be done by a layman as long as local code requirements are followed AC wires must be at least 1 5mm thick and use an outdo...

Page 17: ...round are properly attached and protected so the cable cannot be accidentally moved or damaged Sections coming out of the ground need to be protected by for example a metal U profile 4 Fill out and at...

Page 18: ...llation the junction box K can be wired as shown above If the string inverter is placed on the column of the solar installation the 24VDC transformer can be added to the outdoor junction box K along w...

Reviews: