background image

Cable Entries 
 
Gland the installation wiring into the enclosure using the cable entry points as applicable. 
Connect the 230Va.c input to the Mains Terminal Block as shown in Figure 2. A Mains cable grip is 
provided on the p.s.u chassis which utilises a tie wrap arrangement.  

8. Commissioning. 

 

 
The following procedure is to be followed to safe guard equipment and prevent personal injury. The 
equipment uses dangerous voltages and stores electrical energy, therefore commissioning and testing 
must be carried out by qualified personnel. 
 
All electrical installation and testing must be carried out in line with BS7671: 1992. 
Commissioning Procedure  
 
1. 

Carry out visual inspection and carefully check for any damage, which may have occurred 
during transit. 

 
2. 

Equipment should first be checked to ensure that any connections, which may have become 
loose during transit are tightened. 

 

3. 

Ensure that all external cables to be connected to equipment are suitably rated. Also check that 
all cable glands are correctly earthed.

 

 

As a minimum: 
i) 

Carry out a visual inspection of the installation for compliance to the regulations and 
is free of damage.   

ii) 

Check the protective conductor continuity. 

iii) Measure 

insulation 

resistance 

iv) 

Verify the polarity of the conductors. 

v) 

Measure the earth loop impedance. 

vi)          Test the operation of any ELCBs. 
(refer to BS7671 for full details) 

 
4. 

Please note megger test equipment is not permitted to be used while connected to the 
power pack, otherwise will cause serious damage to internal components.  

     

5. 

As the equipment relies primarily on natural convection for cooling purposes, it is important 
that the enclosure is checked / sited in a position with a free flow of air. This also applies to 
equipment fitted with cooling fans.   

 
6. 

Connect the A.C mains supply to the mains terminal, making sure to connect to the input 
voltage stated in manual. Connect the earth connection to the earth stud provided and check  
all other earth points are firmly connected. 

 
7. 

Before connecting any other external connections remove the mains fuse. Switch on the A.C 
mains supply and check supply voltage and polarity are correct. Replace the fuse and check 
that the power supply unit indicates the correct indications as per the information contained in 
this document. Check power supply D.C output voltages are correct as per the information 
contained in this manual.   

 
8. 

Caution to be exercised when connecting batteries, ensure correct polarity is observed, ensure 
correct battery type (2 x 12V sealed rechargeable lead acid) is used.     

 
There are no user serviceable parts and no user functions. All maintenance and repair work must only 
be carried out by authorised and fully trained How Fire/C.E.L personnel. 
 
The occurrence of a PSU fault should be indicated at access level 1 (applicable to Fire Alarm System 
applications). If a power supply fault is indicated then call the authorised Service/Maintenance 
Engineer. 

Document Ref: O&M15845T.DOC/Rev 0    22.11.99      Page 8 of 8    Originator KP    Checked By        Approved By

 

 

Summary of Contents for A1584

Page 1: ...cations 6 7 Installation Procedure 7 8 Commissioning 8 1 Introduction Thank you for purchasing this 5A Power Supply Unit This power supply is designed to the requirements of EN54 4 This power supply will provide the user with many years of reliable service NOTE It is important to read this manual before commencing installation Document Ref O M15845T DOC Rev 0 16 11 99 Page 1 of 8 Originator KP Che...

Page 2: ...and other materials can substantially weaken the case WARNING Avoid charging the batteries in float standby applications outside of the range quoted by the battery manufacturer WARNING Do not incinerate batteries If placed in a fire the batteries may rupture with the potential to release hazardous gases and electrolyte VRLA batteries contain substances harmful to the environment Exhausted batterie...

Page 3: ...de power supply whilst the 5VDC output is derived via a regulator on the A1584 controller board In the event of Mains failure the power supply will automatically change over to the standby batteries The power supply has 9 LED status indicators to indicate what type of fault has occurred on the power supply The power supply consists of a steel mounting chassis with the A1584 a switchmode power supp...

Page 4: ...Document Ref O M15845T DOC Rev 0 22 11 99 Page 4 of 8 Originator KP Checked By Approved By ...

Page 5: ...etected by the A1584 a delay of 2 seconds is initiated and if the fault still exists after this delay period the Mains Fault output MF is activated 5 Termination List BATT Battery charger terminal 27 5volts 2 amps max two terminals 2 5mm2 cable max BATT Common 0 volt terminal two terminals 2 5mm2 cable max THERM Thermistor input two terminals 2 5mm2 cable max Mains LNE 2 5mm2 cable max 29VDC INPUT...

Page 6: ...AIN Mains input fault Amber Flashes whenever the DC input from the switchmode unit falls below 28V DC or above 30VDC THERM Thermistor Fault Amber Flashes whenever Thermistor input resistance falls outside its resistance range 800 Ohms to 52kOhms PSU OK PSU Healthy Green Illuminates whenever unit is not displaying any detected faults Turns off whenever charger is checking the presence of the batter...

Page 7: ...nclosure must provide adequate ventilation see battery manufacturer s recommendations The power supply should be mounted on to a metal chassis or back plane using the 4 off M4 x 20mm bolts provided Each of the four bolts should be spaced with the M5 x 6mm spacers provided Figure1 provides information relating to the dimensions and locations of the four fixing holes Earthing Arrangement It is recom...

Page 8: ...not permitted to be used while connected to the power pack otherwise will cause serious damage to internal components 5 As the equipment relies primarily on natural convection for cooling purposes it is important that the enclosure is checked sited in a position with a free flow of air This also applies to equipment fitted with cooling fans 6 Connect the A C mains supply to the mains terminal maki...

Reviews: