O P E R A T O R M A N U A L
- 11 -
OUT to disconnect. Connect the return ring terminal to the brass return stud on the reel.
Make all load test connections to the cable from the reel leads as noted in steps 5 and 6.
7.
Connect the input power cord to a grounded power source (see specifications for input
voltage and frequency). If the distance to a power source is greater than the cord provided,
a grounded extension cord of sufficient ampacity will work.
8.
Operate the MAIN POWER circuit breaker to energize the control circuits. (Check
emergency stop button is out and for External Interlock plug or switch if applicable.)
9.
Place the OPERATING MODE switch in the HIPOT/BURN position.
10.
Voltage must be applied according to specifications from the cable manufacturer or any
other applicable test standards.
11.
Choose the appropriate OUTPUT TAP (9/18/36 kVdc, 5/10/20 kVdc) for the cable being tested.
When changing tap positions the switch must be in position to energize high voltage, allow 20
seconds for the motorized switch to achieve final position.
12.
Be sure to place the COUPLER MODE switch in the DIRECT position.
* * * C A U T I O N * * *
P O T E N T I A L L Y L E T H A L V O LT A G E S
M A Y B E P R E S E N T
13.
With the OUTPUT ADJUST at zero (zero start interlock engaged), depress the START
pushbutton. The START light will glow.
14.
Increase the output by rotating the OUTPUT control slowly clockwise until the desired
output voltage is reached.
15.
Maintain the output voltage for the test time specified in your standard procedures. Leakage
current may be read on the current meter at this time. Should the test cable arc or fail, the
output will collapse to a lower value and the current meter reading will increase.
16.
Burning of the cable for THUMPING can be accomplished at this time by allowing the fault
to burn until the output voltage is at the desired thumping voltage.