Replacing a server blade
The hot-swappable feature of the Hitachi Compute Blade 500 series system
allows server blade replacement with the server chassis power ON. This
procedure describes how to replace a server blade when the server chassis
power is on.
Removing a half-wide server blade
1
.
Put on an anti-static wrist strap.
2
.
Web console login procedure on page 4-3
section.
3
.
Power the target server blade off. See
4
.
Turn on LID LED for identifying the target blade. See
5
.
Turn on the maintenance mode from web console. See
6
.
Identify F/W version and take notes of it. See
7
.
Release the blue lock tab and pull the lever, as shown below.
8
.
Holding the server blade, carefully slide out the server blade from the
chassis and place it on an anti-static mat.
Figure 5-1 Removing the half-wide server blade
Notice:
Do not leave a slot open for a long time. Leaving it open can cause the
overheat problem for other components.
5-4
Replacing parts
Hitachi Compute Blade 500 Series System Service Manual
Summary of Contents for CB 520A A1
Page 26: ...xxvi Preface Hitachi Compute Blade 500 Series System Service Manual ...
Page 152: ...4 64 Common process for replacement Hitachi Compute Blade 500 Series System Service Manual ...
Page 294: ...6 12 Identifying RAID rebuild status Hitachi Compute Blade 500 Series System Service Manual ...
Page 432: ...9 16 Updating firmware Hitachi Compute Blade 500 Series System Service Manual ...
Page 439: ...Change LOM configuration 10 7 Hitachi Compute Blade 500 Series System Service Manual ...
Page 442: ...10 10 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Page 450: ...10 18 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Page 464: ...11 14 Troubleshooting Hitachi Compute Blade 500 Series System Service Manual ...
Page 465: ...Hitachi Compute Blade 500 Series System Service Manual ...