Figure 5-8 Installing 4-blade SMP connection board
Replacing an expansion blade
The hot-swappable feature of the Hitachi Compute Blade system allows the
expansion blade replacement with the server chassis power ON. This
procedure describes how to replace the expansion blade when the server
chassis power is on.
Removing a storage expansion blade
1
.
Put on an anti-static wrist strap.
2
.
Connect Web console. See
Web console login procedure on page 4-3
section.
3
.
Power off the target server blade. See
section.
4
.
Turn on LID LED for identifying the target blade. See
section.
5
.
Turn on the maintenance mode from web console. See
section.
Replacing parts
5-11
Hitachi Compute Blade 500 Series System Service Manual
Summary of Contents for CB 520A A1
Page 26: ...xxvi Preface Hitachi Compute Blade 500 Series System Service Manual ...
Page 152: ...4 64 Common process for replacement Hitachi Compute Blade 500 Series System Service Manual ...
Page 294: ...6 12 Identifying RAID rebuild status Hitachi Compute Blade 500 Series System Service Manual ...
Page 432: ...9 16 Updating firmware Hitachi Compute Blade 500 Series System Service Manual ...
Page 439: ...Change LOM configuration 10 7 Hitachi Compute Blade 500 Series System Service Manual ...
Page 442: ...10 10 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Page 450: ...10 18 Change LOM configuration Hitachi Compute Blade 500 Series System Service Manual ...
Page 464: ...11 14 Troubleshooting Hitachi Compute Blade 500 Series System Service Manual ...
Page 465: ...Hitachi Compute Blade 500 Series System Service Manual ...