20
English
Trigger
Lock lever
Lock position
Free position
●
Never use Nailer unless push lever is operating
properly.
The machine employs a preventive mechanism
for unloaded operation.
The machine enters a state where the push lever
cannot be pushed up. This takes place when the
magazine is not loaded with nails or when the
remaining number of nails becomes less than 6 or 9.
CAUTION
●
Use caution not to throw the push lever tip onto
wood.
Before actually beginning the nailing work, test the Nailer
by using the checklist below. Conduct the tests in the
following order.
If abnormal operation occurs, stop using the Nailer and
contact a Hitachi authorized service center immediately.
(1) REMOVE ALL NAILS AND BATTERY FROM
NAILER.
□
ALL SCREWS MUST BE TIGHTENED.
□
THE PUSH LEVER AND TRIGGER MUST MOVE
SMOOTHLY with pulling back the feeder knob.
Trigger
Push lever
Feeder knob
(2) Installing the battery.
Do not operate the push lever or trigger while
installing the battery.
Battery
Push
Pull out
Insert
Handle
Latch
(3) Turn on the Power switch.
Power indicator
Power
switch
Battery indicator
switch
Nailing operation switch
Nailing operation
indicator
Battery indicator
Turn on the Power switch by push and hold on Power
switch more than 1 second.
Make sure the power indicator is lighting in green,
and nailing operation indicator is lighting in blue.
(FULL SEQUENTIAL ACTUATION MECHANISM,)
NOTE
●
Do not press the push lever and/or pull the trigger
during the process of turning the power switch ON.
Doing so will prevent the power switch from turning
ON.
Light in blue
Light in green
000Book̲NR1890DC̲NA.indb 20
000Book̲NR1890DC̲NA.indb 20
2018/08/22 17:33:59
2018/08/22 17:33:59