Checking procedure before the test run
SMGB0066 rev.0 - 12/2009
Test run
Service Manual
6
Check before start up
•
- Check that the hydraulic connections are tight.
- Check that water pressure is 1 bar minimum.
- Check that the water flow is constant and that the purge of the circuit is correct.
- Check that the protections and electrical connections are in line with the electrical patterns and this leaflet.
- Turning on the heat pump YUTAKI
- Turning on the electric heater EH 6 1. (If necessary)
- The power relays for heater are controlled by the Yutaki controller.
- Set the temperature for water (on YUTAKI) to a value of 55ºC to ensure the engagement of the resistance, whatever
the temperature outside.