9. Installation Instructions
Any works related to boiler installation may be delivered exclusively by personnel qualified,
experienced with use of appropriate equipment. A person delivering installation works may perform
provisions boiler operation, whereas commissioning, inspections and repairs shall be delivered by
HKS LAZAR authorized service only.
Any works related to Smart Fire boiler installation shall be delivered pursuant to applicable state
and European standards, as well as local regulations regarding boiler installation!
In particular always adhere to the following:
Regulation of the Minister of Infrastructure as of 12 April 2002 regarding the technical
conditions for buildings and their locations;
Regulation of the Minister of Infrastructure as of 12 March 2009 regarding the
technical conditions for buildings and their locations;
PN-B-02411:1987 Standard ”Heating systems. Built-in solid fuel boiler-rooms
–
Requirements”;
PN-B-02413:1991 Standard ”
Heating and heat engineering –
Protection of open water
heating installations
– Requirements
”;
PN-B-02414:1999 Standard ”Heating and heat engineering – Protection of closed loop
system heating installations with membrane expansion vessels – Requirements”;
PN-B-02415:1991 Standard ”Heating and heat engineering – Protection of closed loop
system heating networks – Requirements”;
PN-B-02416:1991 Standard ”
Heating and heat engineering – Protection of closed loop
system water heating installations, connected to heating networks – Requirements”;
PN-B-02440:1976 Standard ”Heating and heat engineering – Protection of hot potable water
devices– Requirements”;
PN-EN 12828:2006 Standard ”Heating systems in buildings– Designing of central heating
water systems”;
their amendments or replacing regulations.
9.1 Bringing boiler inside
Bringing the boiler inside should be performed carefully, paying special attention to the electronic
elements and wiring. When it is required to uninstall any element, make notes or photographs to
enable installation in identical manner. It allows for quick installation of those elements and
facilitates work delivered by service engineer.
9.2 Boiler room– boiler position
The room where boiler is to be installed must meet relevant regulations and standards, referring to
the solid fuel boilers. In particular pay special attention to the safety of water and electric
installation, proper ventilation, fume exhaust system and fire safety. The boiler room shall be tight
with efficient ventilation and air supply and shall be separated from other spaces with permanent
walls and tight door to prevent smoke penetration to other spaces, in particular those occupied by
people.
Boiler position in the room shall ensure unrestricted access required operation, maintenance and
repairs. In case of SF11, SF15, SF22, SF31 and SF41 boiler the following requirements apply:
In front of boiler– min. 1000mm;
on side of fuel dispenser– min. 1000mm;
on side– min. 500mm;
SMART FIRE BOILER User Manual
Page 40/55