Only use potable water (clean enough to drink)
to increase the service life of the components in
the Ultra-High Pressure system. Always flush the
water source for several minutes prior to filling
the tank to help ensure that no debris enters the
system. Additionally, the tank should be flushed
frequently with clean, fresh water to prevent the
accumulation of debris that may accidently enter
the tank.
There is a 3” ball valve on the passenger side
bottom of the tank that allows for quick draining
of the tanks when flushing is required and com
-
plete draining for system winterization. Another
3” valve on the passenger side provides drainage
for the wastewater bladder in the rear clean water
tank. A large man-way hatch on the top of each
tank provides access to the interior of the tank or
wastewater bladder for inspection or to facilitate
cleaning.
Remember that the wastewater bladder displaces
clean water in the tank as it fills, causing the site
gauge to show more water than is actually in
the tanks. The site gauge is intended to provide
an accurate indication of the water level during
filling operations only. It is not a reliable level
indicator during operation when the debris tank
transfer pump is being used to collect recovered
wastewater.
Use actual blasting time during operation with an
average pump consumption of 8-9 gallons (30-34
liters) per minute to estimate the remaining clean
water in the tank. To ensure maximum clean water
volume, always completely drain the wastewater
bladder before filling the clean water tank.
Typical Clean Water Fill Connection, Valve and Site Tube
Front Clean Water Tank Man-Way Hatch
Clean Water Tank Three Way Valve
Clean Water Fill Connection & Valve
Summary of Contents for STRIPE SH7500
Page 1: ...75 H Operations Manual...
Page 2: ......
Page 72: ...72 NOTES...
Page 108: ...108 NOTES...
Page 161: ...161 Section 5 Scheduled Maintenance...
Page 167: ...167 Appendix 2 Tools Spare Parts...
Page 168: ...168 Appendix 2 Tools Spare Parts...
Page 169: ...169 Appendix 3 Daily Report Pre Op Checklist 1 877 HOG ROAD WWW STRIPEHOGSUPPORT COM 60...
Page 178: ...178 NOTES...
Page 185: ......
Page 186: ......