It is very important to leak test and flush the collector lines before final connection to the 
tank.  The tank is easily filled and maintained with the boiler drain valve at the bottom of 

the tank.  A union can be installed in the 
collector return line as another fill point.  An 
autofill system is offered as an option.

Electrical power requirements for the system 
are based on the number of options installed on 
the tank.  On residential systems, the low 
power consumption of each component means 
that a 15 to 20 amp, 110 VAC circuit will be 
adequate for all standard systems.  A separate 
electrical circuit and breaker are recommended 
to isolate the solar system from being 
accidentally cut off by other appliances tripping 
the breaker. 

After all piping has been completed, flushed, 
and leak tested, and the wiring finished, the 
system startup procedure can begin.  Make 
sure the pressurized domestic hot water line 
and standard water heater are purged and filled 
with water.

Fill the tank using the boiler drain valve at the bottom 
of the tank, or a union in the collector return line. See 
fig. 2.1.  A hose with female fittings on both ends, such as a washing machine hose, is 
required for the boiler drain connection,.

Fill the tank until the water level is at the bottom of the site glass on the tank.  Check for 
leaks in piping or weld seams.  Then add the WT-1 water treatment in the ratio of 1 
gallon WT-1 to 250 gallons of water as shown in table 2.1.  For domestic hot water only 
systems, the tank may be filled to the top of the site glass.  This leaves several inches 
of air gap at the top of the tank.

HoloTech

tm

 Solar Installation Manual 

5

NOTE

Do not apply power to the controls until all plumbing and 
wiring is complete and the tank has been filled with water. 

Figure 2.1  80 Tank Face. 
           Door is Removed

Summary of Contents for HotoTech

Page 1: ...HoloTechtm Solar Hot Water System Installation Manual Ben Gravely PhD Holocene Technologies 1241 Wicker Drive Raleigh NC 27604 c 2012...

Page 2: ...Frame and Collector Mounting 3 2 Collector Piping 3 3 Pipe Insulation 3 4 Solar Controls and Wiring 3 5 Collector System Startup 4 Domestic Hot Water 4 1 Piping 4 2 Re circulator DHW Controls 4 3 DHW...

Page 3: ...th the less solar energy will be collected The placement of the collectors and the tank should be determined including the routing for piping between the components Shading considerations can be inclu...

Page 4: ...ig 2 1 for examples The tank must be installed on a floor or surface substantial enough to carry the full weight of the tank plus water Table 2 1 shows approximate filled weights of five common reside...

Page 5: ...the wiring finished the system startup procedure can begin Make sure the pressurized domestic hot water line and standard water heater are purged and filled with water Fill the tank using the boiler...

Page 6: ...rray of solar collectors The first is the south facing direction south azimuth and the second is the tilt of the collectors up from the ground both described in section 1 The third angle is critical t...

Page 7: ...ting from the lowest corner of the collector array On the opposite end mark the distance up the roof as shown in fig 3 3 Another method is to hold a bubble level perpendicular to the level line and 1...

Page 8: ...and under the feet with silicone sealant to keep water out Make sure to point the narrow dimension of the feet up and down the roof to prevent damming rain water and trapping leaves and debris The co...

Page 9: ...loTechtm Solar Installation Manual 9 Hi Sensor Location Horizontal Line Drain Slope Line Supply Return Low Sensor Location Figure 3 2 Collector Piping Circuit Figure 3 6 Collector to tank piping layou...

Page 10: ...rray from the lowest corner 2 water exits the collector array from the highest corner 3 the water from all collectors must rise to a common high point before it is allowed to drain back to the tank 4...

Page 11: ...e any water can return to the tank Figure 3 8 d shows collectors arranged vertically and horizontally It is a combination of two b type circuits placed one over the other The same result can be achiev...

Page 12: ...HoloTechtm Solar Installation Manual 12 b c Figure 3 3 Collector Piping Diagrams a Drain Slope d Figure 3 8 Collector piping for arrays in the same plane...

Page 13: ...HoloTechtm Solar Installation Manual 13 Supply Return Supply Return Figure 3 4 Dual Bank Piping Diagrams a b Flow Setter Valves Figure 3 9 Collector piping for arrays on a flat roof...

Page 14: ...rigid foam products Use the next thickness up Insulate all piping between the collectors Apply silicone sealant between the pipe jacket and the collector box to keep water from getting in and wetting...

Page 15: ...s lower temperature water to the heat source The low temperature sensor position is the bottom of the solar tank for collector circuits or the return line of the pool for the pool spa circuits The ter...

Page 16: ...ver the flat part of the sensor not the round part to avoid crushing the body of the sensor Connect the hook up wire to the sensor leads Use wire nuts or crimp connectors and fill with silicone sealan...

Page 17: ...ch to the AUTO position Refer to Table 3 3 Connect a low value resistor low R hot across the COL terminals and observe the controller response The system should turn on since the COL terminals appear...

Page 18: ...dard water heater a supply cold line from the bottom of the water heater and a return hot line to the top of the water heater Figure 4 2 illustrates the piping diagram The dip tube in the water heater...

Page 19: ...rasp the two pipes going in and out of the DHW exchanger Note the flow of water through the exchanger by the change in temperature of the pipes as the water flows through them Recirculator Startup Tur...

Page 20: ...quickly The different electrical circuits of a HoloTechtm solar system are all independent and can be treated separately This simplifies the procedure considerably The circuits are Collectors Domestic...

Page 21: ...sensor 3k and the third simulates the very hot OVT condition 1k Set the controller switch to AUTO and connect the STO COL and OVT resistors to the terminals in the patterns indicated in Table A1 1 No...

Page 22: ...ure vs Resistance HoloTechtm solar controls use 10K thermistor temperature sensors These devices change resistance with temperature They are defined by having 10K resistance at 25 C 77 F HoloTechtm So...

Page 23: ...uns pumps water flow stops Height greater than pump head Air locked lines traps in lines If a pump does not pump water the first test should be to swap out the capacitor If this does not work remove t...

Page 24: ...equirements solar performance and economic benefit that were recognized as authorized analytical methods by HUD the NC Energy Division and the US Army Corp of Engineers He has presented numerous paper...

Reviews: