54
Start-up
mounting rail (DIN rail) according to EN50022.
Installation and wiring have to be performed ac-
cording to VDE 0100 (VDE 0100-410, VDE 0100-
510 etc.). Please consider the technical connec-
tion requirements (TAB) of your energy supplier.
Please observe the hazard information in section
„2 Hazard information“ on page 46 during in-
stallation.
Permitted cable cross sections for the cable bushings of
the floor heating actuator are:
Cable bushings
Cable cross section [mm
2
]
1
(I)
(see fig. 2)
> 5.2
2
(J)
(see fig. 2)
> 8.2
3
(K)
(see fig. 2)
> 3.2
Permitted cable cross sections for connecting to the
connecting terminals of the floor heating actuator:
rigid cable [mm
2
]
flexible cable with/
without ferrule [mm
2
]
0.75 – 1.50
0.75 – 1.50
Summary of Contents for HmIP-FAL24-C10
Page 3: ...1 A G B E C H D F...
Page 4: ...2 3 K I J...
Page 5: ...4 5...
Page 6: ...6 7 Selecttaste dr cken Systemtaste dr cken press select button press system button...