4-5
CHAPTER 4 - INSTAllATION INSTRUCTIONS
MAN0448_Issue 13_01-2010
5704 Control System
005704-M-5001 A03249
1.
INTRODUCTION
A summary of the System 57 controller installation procedures is shown
below:
a. Unpack and check the equipment.
b. Identify a suitable location and check the cabling requirements.
c. Confirm the power supply requirements.
d. Install the Cabinet, 19" Mounting Frame or Panel Cutout as
required.
e. Fit the System 57 rack into the Cabinet, 19" Mounting Frame or
Panel Cutout.
f.
Install the sensors and wire back to the System 57.
g. Check, and if necessary reconfigure, the Four Channel Control
Cards.
h. Wire the sensors to the Quad Relay Interface Card terminal
blocks.
i.
Wire the outputs from the Quad Relay Interface Card terminal blocks
or from the Relay Interface Assembly if used.
j.
Wire the power supply to the DC Input Card.
k. In individually powered applications, wire the power supply to each
Quad Relay Interface Card.
After installation is complete perform the commissioning procedures
outlined in Chapter 5.
The following sections of this chapter provide a detailed explanation of
the installation operations.
2.
UNPACKING
On receipt:
a. Carefully unpack the equipment observing any instructions printed
on or contained in the packaging.
Summary of Contents for 5704
Page 1: ...System 57 5704 Control System Operating Instructions ...
Page 4: ...4 MAN0448_Issue 13_01 2010 5704 Control System 005704 M 5001 A03249 ...
Page 6: ...6 MAN0448_Issue 13_01 2010 5704 Control System 005704 M 5001 A03249 User Notes ...
Page 14: ...1 8 MAN0448_Issue 13_01 2010 5704 Control System 005704 M 5001 A03249 User Notes ...