INSTALLATION INSTRUCTIONS

62-0197-04

VBN2, VBN3 

Control Ball Valve/Actuator 

Assemblies

INSTALLATION

When Installing this Product...

1.

Read these instructions carefully. Failure to follow 
them could damage the product or cause a 

hazardous condition.

2.

Check ratings given in the product data literature 
and on the product to ensure the product is suit-

able for your application.

3.

Installer must be a trained, experienced, licensed 
service technician.

4.

After installation is complete, check out product 
operation as provided in these instructions.

Preparation

CAUTION

Equipment Damage Hazard.
Foreign particles like dirt and metal chips can 
damage the ball seals.

Clean upstream lines prior to installation.

CAUTION

Equipment Damage Hazard.
Improper chemicals can damage the valve.

Use neither aerosol products nor petroleum-
based lubricants.

1.

Clean the lines upstream of particles larger than 
1/16 in. diameter. Open valves fully. Flush entire 
hydronic system of contaminants (welding slag, 

solder, scale, metal chips, etc.) and chemically 
treat water according to local conditions prior to 
operation. 

2.

Proceed with installation once the system specifics 
(expansion/contraction of the system and its 
medium as well as operating pressures) are within 

tolerances.

3.

Eliminate air from system.

4.

Two-way valves are marked to show flow direction.

IMPORTANT

Flow arrows must point in the direction of the 

flow for proper operation.

NOTE: For three-way valve mounting, see Fig. 3 

through 5.

5.

Stem rotation:

a. For two-way valves:

(1) Clockwise to close.

(2) Counterclockwise to open.

b. For three-way valves:

(1) Clockwise to increase B to AB flow.

(2) Counterclockwise to increase A to AB flow.

6.

Valve must be mounted with the actuator/bracket 

above the valve body. Do not install the valve with 

the stem below horizontal or upside down. (See 
Fig. 1 and 2.)

Fig. 1. Vertical valve installation.

Fig. 2. Acceptable valve angle from vertical.

M29518

85

85

M29519A

Summary of Contents for VBN2

Page 1: ...tream of particles larger than 1 16 in diameter Open valves fully Flush entire hydronic system of contaminants welding slag solder scale metal chips etc and chemically treat water according to local conditions prior to operation 2 Proceed with installation once the system specifics expansion contraction of the system and its medium as well as operating pressures are within tolerances 3 Eliminate a...

Page 2: ...e mounting plate positions 6 Rotate mounting plate around valve top to the desired position IMPORTANT Do not rotate the valve stem while the hold down ring is removed This can change the common port from AB to A 7 Lower ring down to valve body and engage it in the new position relative to the mounting plate 8 Tighten screws to valve body securing the mounting plate 9 Reattach the stem assembly to ...

Page 3: ...port normally closed fail safe operation To change this to normally open remove and reinstall the actuator in the opposite orientation as follows a Loosen the shaft coupling bolt using a 10 mm wrench b Loosen all other mounting bolts connect ing the actuator to the mounting bracket and set aside c Remove the actuator from the valve shaft d Move the actuator shaft coupling to the opposite side of t...

Page 4: ...4 95 4 1 16 103 3 1 16 78 B 6 7 16 163 6 1 2 165 6 11 16 170 3 76 4 102 6 5 8 168 6 1 2 165 7 3 8 187 7 178 7 1 16 180 7 7 16 189 6 3 4 171 10 11 16 271 8 1 8 206 1 0 0 5 5112 19 5112 22 SS 5112 20 5112 23 SS 5112 21 5112 24 SS 8 5 16 211 8 11 16 221 8 1 8 206 8 5 16 211 8 7 8 225 9 1 16 230 8 7 8 225 10 1 2 267 8 11 16 221 1 4 0 6 2 4 1 1 2 4 1 1 3 2 1 5 1 4 0 6 C D E F LB KG A C F E D B M31360 I...

Reviews: