UVAHAND 250 GS
H1 / BL
18
# 015264DE-EN c
5.3.
Startup
Electrical connection
Plug the connecting cable of the
UVAHAND 250 GS into the socket (17)
of the ballast unit.
Plug the mains cable of the ballast into
the socket.
The green lamp on the mains switch
(16) does not light up until the unit is
switched on.
DANGER!
The UVAHAND 100 may only be connected to properly
installed power sockets with a protective ground con-
ductor.
Only insert and disconnect the connecting cable when
the ballast is switched off and de-energised.
Switching the UVAHAND 250 GS on and off
Pressing the mains switch (2) on the ballast unit switches the UVAHAND
250 GS on and off.
The UV lamp reaches its full power after approx. 3 minutes.
If the equipment is cold, the ignition process can take up to approx. 60
seconds.
The UVAHAND 250 GS is not equipped with hot restrike.
The unit can be switched on again after an adequate cooling-down phase.
If interrupting work for some time, the ballast should be disconnected from
the mains.
Note
Every switching operation influences the service life of
the lamps. Unnecessary switching on and off should
therefore be avoided.
5.4.
Operation
Operation as a hand-held lamp
For ease of operation, the UVAHAND 250 GS is equipped with a handle
which can be adjusted through 90°.
Startup
Electrical Con-
nection
Switching the
UVAHAND 250
GS on and off
Operation as a
hand-held lamp
1
1
16
17