STEP 12
Install two part number 501E1 (qty. 3) rollers into top 2 holes of door panel.
Using provided CRL SOW wrench and spanner wrench to tighten roller to
door glass. See Figure 15, 16 and 17.
STEP 13
Carefully set door glass on bar for purposes of marking for center guide
only. Hold glass plumb and mark both holes and install center guide (Part
number 505S). See figure 18. It is important to put silicone in screw holes
and properly silicone guide itself to avoid leaking.
NOTE: Guide has two settings. Use tighter setting for 3/8” glass.
STEP 14
Hang door on rail and install bottom roller loosely as in previous step for
top rollers. See figure 19.
NOTE: If having issues getting bottom roller installed see next step
for cam system adjustment to allow extra clearance.